You need to appoint a principal designer on all construction projects involving more than one contractor (including subcontractors). This requirement applies to any type of construction project, including domestic (where the appointment can happen automatically).

When Does A Principal Designer Need To Be Appointed? header image

The principal designer role is required under the Construction (Design & Management) Regulations (CDM). This set of regulations applies to all construction work and is a legal requirement. Every construction project must comply with CDM, and that includes appointing the necessary CDM duty holders.

Even though this role was introduced back in 2015, as the newest CDM duty holder, the principal designer role still gets a lot of questions.

When is a principal designer needed? When do they need to be appointed? And what is a project with more than one contractor? What about domestic projects?

In this post, we will answer all of the appointment questions surrounding the principal designer role.

Appointing the principal designer

A principal designer needs to be appointed on all construction projects involving more than one contractor. That includes subcontractors.

client making appointment in writing

Most construction projects will need a principal designer because most construction projects need more than one contractor. Even a simple painting project might require a scaffolder or plasterer to complete the work.

Under CDM, a principal designer must be appointed:

principal designer appointment flowchart

The client must appoint the principal designer in writing, usually at the very start of the project.

5.—(1) Where there is more than one contractor, or if it is reasonably foreseeable that more than one contractor will be working on a project at any time, the client must appoint in writing—

  1. a designer with control over the pre-construction phase as principal designer; and

A principal designer needs to be appointed on ALL construction projects with more than one contractor. You can see we have placed some emphasis on the word ALL.

Previously, duty-holder appointments such as the principal contractor (and the now removed role of CDM coordinator) did not need to be made on domestic projects. Domestic projects are construction work carried out on your own home, or that of a family member, not connected with a business.

domestic house property

Before 2015 (in the 2007 version of CDM), these additional appointments did not need to be made on non-notifiable projects (projects that didn't need to be notified to the HSE).

But, in 2015 CDM changed.

The principal designer does need to be appointed on both:

And, as a side note, so does the principal contractor role.

On any project with more than one contractor, a principal designer must be appointed.

As you can see, the appointment of a principal designer is often required, and not just on bigger commercial projects. In fact, on most construction projects, big and small.

If you think about it, most construction projects involve more than one contractor. Even if you only book a single contractor for the work, they will often use subcontractors for particular activities on the job. Even if it's only a scaffolder for access or an electrician for a day. If additional contractors will be used at any time then a principal designer and a principal contractor are needed.

Need to appoint a principal designer? Use the principal designer appointment template.

Can there be more than one principal designer?

No, there can only be one principal designer.

With both the principal roles (principal designer and principal contractor), there can only be one at any time. The principal designer is the designer in overall control of the pre-construction phase (everything before work starts on site, e.g. when you are planning the work).

cdm duty holder diagram

The reason why there can only be one principal designer on a project is that they are the main point of contact for other duty holders (designers and contractors). And they coordinate all of the information at this stage.

So, you may have multiple designers involved, but only one principal designer.

When should you appoint the principal designer?

Because of their important role in the planning stages of the project, the principal designer is one of the first appointments that should be made.

The principal designer has a wide range of duties to discharge before any work begins on the site and has overall responsibility for health and safety during the planning stages of the project. They should be appointed right at the start of the project before any construction work starts, and ideally, before the design work starts!

5.-(2) The appointments must be made as soon as is practicable, and, in any event, before the construction phase begins.

What if you don't appoint a principal designer?

Under CDM the client must appoint a principal designer. So if you don't appoint a principal designer, there are a couple of different scenarios depending on if the client is domestic or commercial.

On domestic projects, if the client does not make the appointment in writing, the designer in control of the pre-construction phase of the project is the principal designer, and this appointment is automatic.

principal designer appointment flowchart

On commercial projects (construction projects in connection with any business), if the client does not make the appointment, they are automatically the principal designer, and responsible for all the duties and requirements of that role.

(3) If the client fails to appoint a principal designer, the client must fulfil the duties of the principal designer in regulation 11 and 12.

When does a principal designer not need to be appointed?

Since the principal designer role needs to be appointed on all construction projects with more than one contractor, it's not needed on projects with only one contractor.

If you have only one contractor involved in your project for its duration (and they will not use any subcontractors), then you don’t need to appoint a principal designer.

But you shouldn't wait until you have more than one contractor before appointing the principal designer. As discussed earlier, the principal designer should be one of the first appointments made.

architect marking up construction drawings

The regulations are quite clear that the appointment should be made "Where there is more than one contractor, or if it is reasonably foreseeable that more than one contractor will be working on a project at any time", so if it is likely you will need more than one contractor on the project, then get your principal designer in place from the beginning.

It is worth noting that even if you have another contractor who is only doing a small amount of work, and is not on the site every day, that is still more than one contractor. If your contractor subcontracts part of his work, for example to a plumber or electrician, that is also more than one contractor.

As many projects require expertise from different trades, even small projects will usually need to appoint a principal designer.


Need to understand your CDM requirements? Read the free CDM duty holder guides, and use the free CDM compliance checklist to help you!

share on twitter share on facebook share on linked in share by email

This article was written by Emma at HASpod. Emma has over 10 years experience in health and safety and BSc (Hons) Construction Management. She is NEBOSH qualified and Tech IOSH.

Need CDM Help?

Get CDM support on your construction projects with our free guides and support packs for all duty holders.

CDM Support

Recent posts like this...

Does CDM Apply To Refurbishment? image

Does CDM Apply To Refurbishment?

Yes, the CDM regulations apply to every type of construction project, including refurbishment work. It may surprise you to know that the refurbishment project doesn't even have to involve any structural changes for CDM to apply.

Read Post
Does CDM Apply To Non-Notifiable Projects? image

Does CDM Apply To Non-Notifiable Projects?

Construction projects that do not meet the CDM notification thresholds are known as non-notifiable projects. Being non-notifiable means they do not need to be notified to the HSE. Other than not being notifiable, the CDM regulations still apply - in full!

Read Post
When Are You Responsible For Subcontractors Health And Safety? image

When Are You Responsible For Subcontractors Health And Safety?

Subcontractors are used on most construction projects. And you might think that each contractor is responsible for their own health and safety - and they are. But if you use subcontractors, you have some responsibility for their health and safety too.

Read Post

Spend less time on paperwork.
Start with the free plan today.